Xingyang Industrial Zone, Zhengzhou, Henan, China

Aggregate Crushing Plant

Design basis, flowsheet, power and capex for 150-500 t/h granite, basalt and limestone aggregate plants, from work index to acceptance testing.

Aggregate Crushing Plant process flow diagram

A 300 t/h granite line making 0-5, 5-10, 10-20 and 20-31.5 mm aggregate from 0-700 mm quarry feed looks simple on a flowsheet, and rarely is. Three numbers decide it: Bond work index (12-20 kWh/t for granite, up to 22 for basalt), abrasion index, which decides whether manganese or chrome white iron survives the chamber, and the flakiness limit the buyer actually enforces.

Design basis: what the feed actually is

Testing before quotation is not decoration. A 20 kg sample and a Bond work index test cost far less than rebuilding a secondary chamber, and they turn a guess into a number you can defend to a bank. We ask for top size distribution, work index, abrasion index, clay and moisture, and the target grading with its tolerance.

Parameter Typical range What it changes
Feed top size 0-600 mm, up to 0-800 mm Primary opening, hopper volume, feeder width
Bond work index 12-22 kWh/t Installed kW, reduction split between stages
Abrasion index 0.2-0.6 Chamber profile, liner alloy, wear cost per tonne
Feed moisture 1-6 percent Screen aperture, washing need, blinding risk
Clay and fines 3-15 percent passing 5 mm Scalping, water demand, pond sizing
Bulk density 1.5-1.8 t/m3 Conveyor width, stockpile and silo loads
Flakiness limit 15-25 percent by mass Whether an impactor is needed at all

The work index sets power; the abrasion index sets the maintenance budget, and the two do not correlate. High work index with low abrasion rewards a cone on manganese. Moderate work index with high abrasion punishes any impactor. Moisture above 4 percent changes screen aperture choice and is the usual reason a plant misses capacity on a wet morning.

Two stages or three

Jaw plus cone suits limestone-like rock, modest reduction and sub-base product. Three stages, with secondary cone and tertiary cone or VSI in closed circuit, appear when 5-10 and 10-20 mm clean stone are sold separately and flakiness is tight. If 700 mm must reach 20 mm and a cone cannot exceed about 4:1 per pass, a third stage is required.

Choosing the reduction machine

Primary: jaw for hard abrasive rock to 800 mm, because the compression chamber tolerates slabs and wear parts are cheap per tonne; gyratory above roughly 500 t/h, where uptime beats capital. Secondary: standard or coarse cone for granite and basalt, since laminated breakage gives denser, more cubical product at lower liner cost than impact. HSI fits soft to medium rock with abrasion below about 0.3 and cubicity as the priority;.

Tertiary: short-head cone in closed circuit for shape, or VSI where the flakiness limit is severe. VSI costs more power per tonne and makes more fines, so it is chosen by specification, not habit. Screens: three-deck inclined units, polyurethane or rubber media, apertures 10-15 percent above the nominal cut to allow for moisture.

Circulating load is designed, not discovered. Closed tertiary circuits run 60-120 percent; below 50 the screen is oversized, above 150 the crusher bottlenecks. We size the deck on fresh feed plus circulating load and print the assumption on the flowsheet.

Shape, dust, water, stockpiles

Cubicity follows reduction ratio and chamber geometry. Keep cone reduction below 4:1 and the chamber choke-fed; granite then lands at 10-18 percent flakiness. At 6:1 the slab count climbs, and a VSI becomes cheaper than rejected product.

Dust control is two systems with two budgets. Sprays at transfer points and crusher discharge hold the plume down at 0.5-1.5 m3/h per point, limited by the moisture screens tolerate. A baghouse answers permits written in mg/m3: size on total exhaust, typically 8,000-25,000 m3/h at 300 t/h, at an air-to-cloth ratio of 1.0-1.2 m/min on pulse-jet bags.

Washing is a separate decision. Clay passing 5 mm above about 5 percent needs a washing screen or log washer at 1.0-2.0 m3 per tonne washed, mostly recovered; that number drives thickener area, pond volume and make-up water, and it is the item most often missing from a first budget.

Stockpiles follow the loader. Conical piles give 300-800 t live and segregate; a reclaim tunnel costs more but blends. Size live capacity at 8-12 hours of each product.

Power, capacity and capex

Three-stage hard rock runs 1.1-1.6 kW per t/h installed: 300 t/h is 380-480 kW connected, with diversity 0.75-0.85 for the supply agreement. Bands below are indicative for equipment engineered in Zhengzhou and built with selected partner factories in Henan, shipped as modules; freight, duty and local erection are excluded.

Scope 150 t/h 300 t/h 500 t/h
Primary station, feeder and hopper 140,000-190,000 210,000-290,000 320,000-430,000
Secondary and tertiary crushers 260,000-360,000 480,000-680,000 780,000-1,050,000
Screens, conveyors and chutes 180,000-250,000 330,000-460,000 540,000-720,000
Civils and steel structure 220,000-300,000 400,000-560,000 650,000-880,000
Electrical, control and cabling 90,000-130,000 160,000-230,000 260,000-360,000
Dust, baghouse and water systems 70,000-110,000 130,000-190,000 210,000-300,000
Total installed, indicative 960,000-1,340,000 1,710,000-2,410,000 2,760,000-3,740,000

Layout, civils and power distribution

Layout follows two constraints: the angle at which a conveyor lifts damp aggregate without rollback, and the turning circle of the largest site truck. Primary-to-secondary transfer stays below 18 degrees, walkways are 1.2 m each side.

Civils carry surprising loads. A 300 t/h plant puts 60-120 t static on the primary foundation plus dynamic factors of 1.5-2.0. The cone foundation needs 3-5 times crusher mass to absorb stroke. Screen steel takes 1.0 kN/m2 live plus wind, and chutes are lined above 6 m/s impact.

Commissioning hold points and acceptance

  1. Foundation and anchor survey signed before grouting.
  2. Four-hour no-load run of every motor, temperatures logged.
  3. Closed-side setting verified by lead pour, not by gauge.
  4. Screen stroke and amplitude checked loaded and empty.
  5. Water and dust systems balanced at design flow.

Acceptance runs 72 hours at the stated setting. Capacity comes from a belt scale over a full shift; grading is sampled from each stockpile and flakiness is tested on the 10-20 mm fraction. Availability of 85 percent with sustained capacity is the pass mark; anything short becomes a punch item with an owner and a date.

Questions we answer before quotation

Can one plant make sand and aggregate?

Yes, by adding a VSI and a split screen after the tertiary. Sand reduces aggregate yield and roughly doubles the fines you must capture or sell.

How long does erection take?

Ten to fourteen weeks for 300 t/h on a prepared site with local labour and one supervisor.

Can it run on generators?

Yes, at 1.25 times connected load with soft start or a VFD.

Send top size distribution, work index, abrasion index, moisture, clay and the grading you must sell. We return a flowsheet, a power schedule and a capex band against those numbers, and say where the risk sits.

Manufacturer and compliance facts

Henan MSK Machinery Co., Ltd. designs and commissions complete plants and recycling lines from its engineering office at Xingyang Industrial Zone, Zhengzhou, Henan, China; fabrication is carried out with selected partner factories in Henan, inspected before shipment. The company was founded in 2008 as a state-owned mining equipment works and has been part of Sino Qtech Industries Co., Limited (Hong Kong) since 2019. Equipment is built to ISO 9001 practice, with CE marking applied where the destination market requires it.

Legal entityHenan MSK Machinery Co., Ltd.
WorksXingyang Industrial Zone, Zhengzhou, Henan 450100, CN
Second siteGongyi — castings, wear parts, heat treatment
Export contractorSino Qtech Industries Co., Limited, Hong Kong
Quality systemISO 9001 practice; CE on request
Contact+86 133 5377 2661 · [email protected]

References used in this page’s engineering claims: EU WEEE Directive 2012/19/EU · Basel Convention on waste shipments · US DOE — Waste Reduction & Recycling · ISO 9001 quality management

Tell us the material and the tonnage

We size the line from your feed analysis, not from a catalogue page — proposal and layout within one working week.