2 t/h Lithium Battery Sorting Line
Two tonnes an hour is the first battery size that behaves like an industrial plant rather than an workshop. It takes whole automotive modules, runs two crushing trains so a single fault does not stop production, and produces half a tonne of black mass an hour — enough to negotiate an offtake instead of accepting whatever a trader offers.
Feed envelope and the pack bay
Automotive modules up to 60 kg, e-bike and power-tool packs in bulk, and consumer cells in collection drums. Vehicle packs are opened in the pack bay, not on the line: the bay needs a two-post lift, an insulated tool set and a thermal camera, and it is where the state of charge is first read.
| Feed | Accepted | Constraint |
|---|---|---|
| Automotive modules | Up to 60 kg | Busbar cut at the bay, not the bench |
| Prismatic cells | Up to 40 kg | Discharged to below 1.0 V |
| Cylindrical cells | All common formats | Loose cells fed through a drum tipper |
| Packs | Up to 400 kg, opened at the bay | BMS retained for the discharge log |
| State of charge | Below 30 % into the line | Rack capacity sets inventory |
| Quarantine | Swollen, leaking, fire-damaged | Steel drum, separate campaign |
The pack bay is also the plant’s main fire risk after the rack. It is separated by a two-hour wall, drained to a containment sump, and fitted with a deluge head above each lift position — a detail that costs little at build stage and cannot be retrofitted economically once the electrical rooms are in.
Two trains, one scrubber
| Station | Function | Power | Control point |
|---|---|---|---|
| Discharge rack | Resistive discharge, per-bay logging | 16 kW | Voltage below 1.0 V before release |
| Inert dismantling | Two benches, BMS and casing removal | 26 kW | O₂ below 8 % at each bench |
| Crusher (×2) | Water-cooled, 1 t/h each, independent | 95 kW | Bearing temperature alarm |
| Density separation | Black mass, foil, separator, casing | 40 kW | Purity ≥ 96 %, Cu below 1 % |
| Magnetic and eddy stage | Steel and aluminium recovery | 20 kW | Steel fraction clean of copper |
| Off-gas and scrubbing | Shared HF and electrolyte control | 24 kW | Continuous stack monitoring |
Two trains cost about 15 % more than one large crusher of the same total capacity, and they buy redundancy that matters: a crusher rebuild takes three to five days, and a plant with one train loses a week of production for a wear part. The shared scrubber is the opposite decision — two scrubbers would double the monitoring obligation without improving capture.
Layout and services
The process building is 30 × 9 m, with the pack bay and rack in an attached 12 × 8 m compartment. Nitrogen, water and power all enter at the compartment wall so that the process room has no penetrations below 2.5 m — a fire-separation detail that inspectors look for first.
| Service | Requirement | Note |
|---|---|---|
| Electrical | 240 kW installed, 315 kVA supply | Crushers on soft starters, interlocked |
| Nitrogen | 55–75 Nm³/h | PSA plant with 4 h buffer |
| Compressed air | 6 bar, 2.0 m³/min | Oil-free, dried to −40 °C |
| Water | 5 m³/day | Crusher cooling and sump make-up |
| Ventilation | 8 air changes/h, process room | Negative pressure to scrubber |
| Floor | 5 t/m² under crushers | Isolated pads, 20 mm gap |
Cost per tonne, and where it hides
| Item | Value | Notes |
|---|---|---|
| Energy per tonne | 50–78 kWh | Crushers and density stage dominate |
| Nitrogen per tonne | 1.6–2.3 t | Better than small lines, still significant |
| Black mass output | 250–350 kg/t | 96–98 % purity, 500–700 kg/h |
| Foil and casing | 350–450 kg/t | Copper and aluminium, sold separately |
| Crew | 7 per shift | Two per train, two on feed, one control |
| Capital, indicative | USD 820k–1.15M | EXW, excluding civils and N₂ plant |
Labour is the line item that surprises buyers: seven people a shift is 21 across three shifts, and at 2 t/h that is a real cost per tonne. Automation of the dismantling benches is possible but rarely justified below four tonnes an hour, because the feed variety defeats fixed tooling.
Buyer scope and the traps
Buyer scope covers the buildings and fire compartments, the 315 kVA supply, the nitrogen plant and its buffer, water and sump, the scrubber discharge permit, the pack-bay lift and tooling, and a 3 t forklift. Erection and commissioning take four to five weeks with a witnessed inert test and a 72-hour continuous run before acceptance.
The first trap is sizing the rack to the line rather than to the collection cycle. At two tonnes an hour the rack needs 40–60 t of inventory to keep the line fed through a normal delivery week, and that inventory is both a fire load and working capital. The second is accepting a quotation that lists “crusher” without stating whether the inerting is on the crusher inlet, the discharge, or both — the difference is a machine that meets its permit and one that does not.
Below about 1.2 t/h the single-train line is the better buy; the redundancy argument only pays once the plant runs more than two shifts.
MSK Machinery offers this size with the pack bay designed to the buyer’s local fire code rather than a generic layout. The plant is manufactured by Henan MSK Machinery Co., Ltd. of Xingyang, Zhengzhou, Henan, and the trading entity can be verified through https://sinoqtech.en.alibaba.com/ before contract signature.
Related pages
MSK network
Aggregates and mining equipment: mskmachinery.com. Export contracts: Sino Qtech Industries.
Manufacturer and compliance facts
Henan MSK Machinery Co., Ltd. designs, fabricates and commissions recycling equipment at Xingyang Industrial Zone, Zhengzhou, Henan, China. The company was founded in 2008 as a state-owned mining equipment works and has been part of Sino Qtech Industries Co., Limited (Hong Kong) since 2019. Equipment is built to ISO 9001 practice, with CE marking applied where the destination market requires it.
References used in this page’s engineering claims: EU WEEE Directive 2012/19/EU · Basel Convention on waste shipments · US DOE — Waste Reduction & Recycling · ISO 9001 quality management
Questions buyers ask before the proposal
How much black mass does the plant make in 1 day?
At 250–350 kg per tonne of feed and 16 t a day at full rate, output is 4.0–5.6 t of black mass a day. That is a full truckload every four to five days.
Why 2 crushers instead of 1 larger unit?
Redundancy. A single 2 t/h crusher rebuild costs three to five days of production; two 1 t/h trains keep half the plant running. The capital premium is around 15 %.
What inventory does the rack need for 1 week?
40–60 t of packs for a normal weekly delivery cycle, held in a separate fire compartment. The rack, not the crusher, sets how much capital sits in the yard.