Vietnam
Battery pack sorting, Bac Ninh
An e-waste collector receiving mixed NMC and LFP packs from two-wheelers needed grading before shredding, not after.

What the project had to solve
The plant had been shearing whole packs, which put unknown-state cells into the shredder and caused two small fires in the first year. Our scope started at the isolation table: discharge racks, per-module testing and a graded release to the shear.
Nineteen percent of incoming modules tested well enough for second-life assembly. That stream now goes to a pack builder instead of the crusher, which changed the economics of the whole plant more than the black mass recovery did.
Residual voltage is logged per pack and retained for 24 months, which satisfied the client’s insurer and is now part of their downstream due-diligence pack.
| Input | Mixed NMC / LFP packs |
|---|---|
| Reuse rate | 19% of modules |
| Commissioned | 2024 |
| Safety | Discharge + gas detection |
Similar project?
Send the material, the tonnage and the permit limits you have to work inside. We will tell you which parts of this design transfer and which do not. Sister site: mskmachinery.com.
Manufacturer and compliance facts
Henan MSK Machinery Co., Ltd. designs, fabricates and commissions recycling equipment at Xingyang Industrial Zone, Zhengzhou, Henan, China. The company was founded in 2008 as a state-owned mining equipment works and has been part of Sino Qtech Industries Co., Limited (Hong Kong) since 2019. Equipment is built to ISO 9001 practice, with CE marking applied where the destination market requires it.
References used in this page’s engineering claims: EU WEEE Directive 2012/19/EU · Basel Convention on waste shipments · US DOE — Waste Reduction & Recycling · ISO 9001 quality management
Questions buyers ask before the proposal
How long did commissioning take?
Between three and six weeks on site, including operator training and the acceptance run on the customer’s material.
Would the same design work at our site?
Partly. The separation sequence transfers; the thermal sizing, stack arrangement and layout are recalculated against your feed and permit limits.