Commissioning a 300 t/h Steel slag Plant: Sequence and Hold Points

Commissioning a Steel slag plant at 300 t/h runs in three phases: dry checks, load in stages, and settling the circulating load. Each has hold points that should be signed before the next begins, because a fault found in phase one costs a fraction of the same fault found in phase three.

Commissioning and ramp-up

Dry checks cover alignment, torque, guard fit, belt tracking and interlocks. Load testing starts at half feed for four hours, watching amps and bearing temperatures. Only when the readings are stable does the feed go to design rate.

Ramp-up is where the plant finds its real capacity. Expect two to four weeks to settle screens, settings and the recirculation. Record the belt scale at every stage each shift; the trend tells you more than any single reading, and it is the record that settles disputes later.

What we need from the owner

Feed sample and analysis, target output and specification, site location and power available, and the commercial model for the product. With those we issue a mass balance, an equipment list, a power demand and a budget range before any drawing is committed.

Where this fits

Route: Construction & demolition. Feed: Steel slag from a steelworks stockpile, bulk density 2.90 t/m³, work index 18–24 kWh/t. Product: road-base aggregate and recovered metal.

Related: solutions index · process routes · request a proposal.

Factory direct

Tell us your feed material and target output

We size the machine or line, confirm power and layout, and send a written quotation within one working day.

Home Solutions Cases Contact WhatsApp